Field for tracking changes to a task ?
The "created" field tells when a task was created. You can always do a
direct comparison between start and baseline start - same is true for any of
the baseline fields. There is no built-in field to track changes to task
names etc. You could implement something using the task change event.
--
Please try to keep replies in this group. I do check e-mail, but only
infrequently.
-Jack Dahlgren, Project MVP
+++++++++++++++++++
Quote:
> Does anyone know if there is an MS Project field that tracks new and
> existing tasks? In other words, I want to see if a task has changed
> (be it the task name, cost, or date) or added to the project. (be it
> from last save, baseline, or something), by using the field/attribute.
> Thanks in advance.