After adding tasks outside of MS Project, saving in MS Project deletes them
Don't worry, if you take a look at the database table, everything is
there. You need to set the "text_field_set" on project_information
table to be 1 in order to see the information you inserted not via MS
project. customer_date_field_set and customer_number_field_set are
other two fields that need to be set to 1 if you insert date or number
infomation via non-project means.
Botao
Quote:
> hi -
> need help! I use a web interface to create a new Project and add tasks to
> it. When I open the project within MSP2K, and save the project - the project
> and all its tasks are deleted! I'm not sure what's going on - I have been
> setting all the EXT_EDITED columns - just not sure what's happening -
> help!
> Stephanie