I need to be able to show a user defined column that will have one of 3
states, based on the actual v expected values for costs and duration of
tasks.

The first state will be "OK - the task is on track", the second will be
"WARNING - task is 25% or more away from its estimate", and the third
"PROBLEM - task >25% away...".

What is the best way to achieve this ? I am assuming that if a baseline has
been set, then I should be able to look at percent complete, and check that
against the portion of the task that was scheduled to be completed against
the status date, and from there work out if the task is on schedule or not ?

It seems that this would probably be a standard requirement - so does anyone
know if this is built in to Project or not ? I can't seem to see it !

Thanks,

Paul.



Tue, 30 Nov 2004 20:26:05 GMT  
 User defined column to show task progress...
Hi Paul,

Have a look at Customising columns and setting Graphic Indicators in the
Help screens.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:-)

Mike Glen
MS Project MVP


Quote:
> I need to be able to show a user defined column that will have one of 3
> states, based on the actual v expected values for costs and duration of
> tasks.

> The first state will be "OK - the task is on track", the second will be
> "WARNING - task is 25% or more away from its estimate", and the third
> "PROBLEM - task >25% away...".

> What is the best way to achieve this ? I am assuming that if a baseline
has
> been set, then I should be able to look at percent complete, and check
that
> against the portion of the task that was scheduled to be completed against
> the status date, and from there work out if the task is on schedule or not
?

> It seems that this would probably be a standard requirement - so does
anyone
> know if this is built in to Project or not ? I can't seem to see it !

> Thanks,

> Paul.



Wed, 01 Dec 2004 05:05:05 GMT  
 
 [ 2 post ] 

 Relevant Pages 

1. Query ony showing *(All Columns) no columns are shown

2. Accessing User defined Outlook 2k tasks from VB

3. Referencing Outlook 2k Task User Defined Fields

4. User-defined error when the user doesn't define any errors

5. User Control - User-defined type not defined

6. User Defined fields values not showing

7. Custom icon in user defined Column

8. Custom Icon in User Defined Column in Outlook

9. How do I display a progress bar showing progress for database replication

10. How do I display a progress bar showing progress for database replication

11. Progress or something to let user know script is in progress (WSH, not HTML)

12. User Defined Type Not Defined

 

 
Powered by phpBB® Forum Software